In 2014, FRASCATI C.V. was awarded by ARDEOLA C.V. a company incorporated and existing according to the laws of the Netherlands with the Contract for the execution of the following Services: Detail Engineering and Technical Assistance, Routine Tests, Personnel Training, Supervision of Installation and Commissioning of the Equipment associated to the Project "Construction of the Substations: Angostura 400/115/13.8 kV, Centro 115/13.8 kV, Marhuanta 115/13.8 kV, Cayaurima 115/13.8 kV and Farallones 115/34.5/13.8 kV; and the Supply and Installation of the Transmission Lines and Distribution associated to the Ciudad Bolívar Transmission System”.  

 

In 2010, FRASCATI C.V. was contracted by SDV ENERGY AND INFRASTRUCTURE, S.L. an international company headquartered in Madrid, Spain, dedicated to the engineering, procurement, construction and maintenance of industrial and electrical infrastructure projects in Latin American countries, to execute in Venezuela the Detailed Engineering of the following Projects:
 
• ENGINEERING,PROCUREMENT AND ELECTROMECHANICAL INSTALLATION OF THE SUBSTATIONS ASSOCIATED TO THE BACHAQUERO PLANT TRANSMISSION INTERCONNECTION.

• ENGINEERING, PROCUREMENT AND CONSTRUCTION OF THE 115/13,8 KV SUBSTATION.

The scope of the work executed by FRASCATI C.V. included the following activities:
- Substation Planialtimetric Surveys.
- Soil Studies for the Substations.
- Resistivity Studies for the Substations.
- Hydrological Studies.
- Environmental impact studies.
- Detailed Engineering of Civil Works for the Substations.
- Detailed Engineering of Electromechanical Works for the Substations.
- Detailed Engineering of Mechanical Works for the Substations.
- Detailed Engineering of Protection Works, Numerical Control, Measurement and Communications for the Substations.
- Routine Testing and Operational Staff Training.
- Installation Supervision.
- Commissioning.